Location: Monclova ,Coahuila. Amount negotiated: $ 20,878,799.00 USD. Contract, Addressed to customer.
Design and construction of offices building and complex , 34,000m2 |
Ground movement 150,000 mts3. |
System for deep foundation piles , +1.200 tons of steel structure based armor and joist . , Tilt up walls with martelinados finishes and plating with KR -1 , concrete foundations for machinery and equipment, more than 30,000 m2 of floor laser leveled |
High and Low chrage centers, fire prevention system, HVAC Mechanical, etc. |
Turnkey project. Elapsed Time: 11 months.