EL PROYECTO

Calcium Carbonate production plant divided in three phases IA-IB-IC, that include the construction of a primary crushing area, a storage room of 15,000 sq. ft., a production building of 130 ft. high and 16 storage silos.

NÚMEROS

Total execution time: 13 months (engineering-construction-startup).
85,000 cu ft concrete.
150 tons of reinforcement steel.
22,000 sq. ft. concrete floors.
1,500 Tons of metallic structure.
20,000 sq. ft. of grid floors Irving type.
9000 sq. ft. of metallic floors with skid plate.
3,600 ft. of hand rails.
57,000 sq. ft. of cover and facade sheet.
334 tons of mounted equipment in more than 300 machines.
1,500 ft. of belt conveyors.

EXTRAS

9 professionals at work (Engineers, Architects, Technicians). Hand labor: monthly average of 98 people.