Winning project in CEMEX International Awards XVIII edition, categories: Industrial Project / Construction Innovation.
Execution time: 12 months. |
More than 62,000 sq. ft. construction. |
10´600,000 cu ft Earth moving. |
450 deep foundation piles. |
Warehouses designed based on rigid frames, screwed for better precision and speed; adding up more than 3,600 tons of steel. |
Concrete bases of more than 500,000 cu ft concrete. |
Interconnection tunnels and ditches of more than 15,000 ft. |
3 water cisterns that add up to 120,000 cu ft capacity. |
Sewage treatment plant. |